Changing a bathroom floor in an HDB flat

Six rules, in HDB's words where we can. If HDB's pages and ours differ, follow HDB's.

Ben

Six rules. Check each one against HDB's page before work starts.

  1. 1

    In a new block, the toilet floor and wall finishes that HDB or the developer provided can't be replaced for 3 years from the block's completion date. New toilet floor finishes can be laid over them with adhesive.

    HDB's reason: the waterproofing membrane under a toilet floor "prevents water from leaking through the floors into the ceiling of the flat immediately below."

  2. 2

    After those 3 years, replacing a bathroom or toilet floor needs an HDB permit.

  3. 3

    When a bathroom or toilet floor is replaced, pre-packed waterproofing screed and a waterproofing membrane must go down first, with the membrane turned up at least 150 mm against the walls, kerbs and pipes. The floor traps get UPVC gratings with long collars, and finishes and screed together come to 50 mm or less.

  4. 4

    When a replaced bathroom floor is finished, you and your contractor must test it with water.

  5. 5

    Laying new floor finishes over the old ones with adhesive only needs no permit if, in HDB's words, there is "only 1 layer of existing floor finishes including cement screed", the new finish and its adhesive come to 13 mm or less, the floor trap isn't touched, and the work doesn't cause "backflow or lateral seepage into the bedroom".

  6. 6

    Use only contractors from HDB's Directory of Renovation Contractor (DRC), even for work that doesn't need HDB's approval.

    In our directory, look for ✓ HDB DRC Listed. The hours and days for taking a floor up are on No. 01's rules page, "Removing floors in an HDB flat".

Find who can lay it
Notes and sources (8)
  • HDB, Renovation: important information · checked 30 Sep 2026

    • "A waterproofing membrane is laid on the cement screed before laying floor finishes in toilets. This prevents water from leaking through the floors into the ceiling of the flat immediately below. The toilet floor and wall finishes provided by HDB/ developer must not be replaced for a period of 3 years from the completion date of the block for this reason. You can, however, lay new toilet floor finishes over the existing floor finishes using adhesives."
    • "Pre-packed waterproofing screed and waterproofing membrane must be used in bathrooms/ toilets before laying new floor finishes. Membrane should be upturned (minimum 150mm) against the walls, kerbs, and pipes"
    • "UPVC floor trap grating with long collar must be used at the floor traps when carrying out replacement of floor finishes"
    • "You and your renovation contractor must conduct a water test on the bathroom/ toilet upon completing the replacement of floor finishes"
    • "Engage only contractors from the Directory of Renovation Contractor (DRC) to carry out the renovation, including those works that do not require HDB's approval"
  • HDB, Building works guidelines · checked 30 Sep 2026

    • "Replacement of existing bathroom/ toilet floor finishes after first 3 years from the date of completion of the block." Permit required: yes.
    • Replacement of existing bathroom/ toilet floor finishes after first 3 years: "Total thickness of finishes and screed must not exceed 50mm"
    • Laying of floor finishes over existing floor finishes using adhesive only, permit required: no. "There should be only 1 layer of existing floor finishes including cement screed before proceeding to lay the additional layer of floor finishes"; "Thickness of the floor finishes inclusive of the adhesive must not exceed 13mm"; "No tampering of the floor trap is allowed"; "Work should not result in backflow or lateral seepage into the bedroom".